AL Topping out Ceremony
2019-05-29 10:51 AM
On the afternoon of May 3, 2019 The Project Management Board of An Lac held a Topping Out Ceremony.
 
With experience, competence and enthusiasm, An Lac site team has completed construction of 6-day structure to pour 1 concrete floor, 
8-month round construction from excavation of basement and 20-storey roof. 
 
  
 
 
The progress of ensuring smooth floors is 6 to 7 days for 1 floor. 
Still working on traditional film overlay method compared to other companies usually completed about 8-10 days for 1 floor.
Similar to the following finishing works: building, painting, tiling, and water painting are also 7 days 1 floor. 
 
That is a very proud achievement. The project is expected to be completed within 15 months from the
foundation excavation work to the acceptance of fire protection and handover. Currently, the construction site is under construction as the 10th month.
The roofing ceremony took place successfully with the participation of: Investors, Supervision consultant, Structural contractor, Finishing contractor, MEP and more.
 
 
 
 